2026 EBS pollock assessment dashboard
Schedule, data readiness, bridge progress, and review status
Note

This is a read-only summary of six CSV tracking files in this assessment-year folder. Edit those files—not the boxes or tables on this page—and the dashboard updates the next time Quarto renders the project.

The inventory is current as of August 7, 2026. Located; needs checking means a possible input file has been found, but its owner, version, units, processing, and suitability still need confirmation. Ready for assessment use means those checks are complete. Awaiting delivery means the expected input has not yet been received. Open decisions are unresolved choices recorded in the review tracker.

Located; needs checking

7

Ready for assessment use

0

Awaiting delivery

5

Open decisions

8

Milestone Target Purpose Status
inventory_start 2026-07-17 Document model history and candidate data inventory active
sporc_september_package 2026-08-25 Complete the SPoRC near-exact bridge package for the September review active
september_data_freeze 2026-09-TBD Freeze inputs for early September draft planned
september_draft 2026-09-TBD Review bridge, model set, diagnostics, and preliminary results planned
november_data_freeze 2026-11-TBD Freeze final assessment inputs planned
november_final 2026-11-TBD Final assessment review and recommendation planned
Bar chart counting 2026 assessment data products by availability status.
Data stream Terminal year Status Next check Target
Fishery catch at age 2025 candidate_available Confirm strata, units, FT-NIRS treatment, and final accepted output September
Fishery weight at age 2025 candidate_available Confirm wtageAE and wtageFTNIR definitions and select final series September
FT-NIRS fishery ages 2025 candidate_available Document calibration, accuracy, precision, and accepted use September
Bottom trawl survey biomass and covariance 2025 candidate_available Confirm provider, version, units, covariance method, and final status September
Bottom trawl survey age composition 2025 candidate_available Identify source table and verify composition extraction September
AVO acoustic product 2025 candidate_available Confirm official series, processing version, timing, and model input September
Combined provisional model input 2025 candidate_available Reconcile every embedded stream to an annual delivery September
2026 bottom trawl survey products 2026 pending Await biomass, covariance, age composition, and diagnostics September_or_November
2026 directed acoustic-trawl survey products 2026 pending Await biomass, age composition, timing, coverage, and diagnostics September_or_November
2026 AVO acoustic product 2026 pending Confirm whether a 2026 product is expected and its delivery date September_or_November
Current-year fishery catch 2026 pending Define September snapshot and November replacement date September_and_November
Environmental and ecosystem indicators 2026 pending Identify required model inputs versus contextual indicators September_or_November
Run Role Parent Purpose Status
bridge_2024 reproduction none Reproduce accepted 2024 results planned
bridge_2025_cie development_bridge bridge_2024 Establish development lineage only; not 2025 advice planned
bridge_2026_data data_bridge bridge_2024 Separate data effects from method effects planned
base_2026 candidate_base bridge_2026_data September candidate planned
base_2026_nov final_candidate base_2026 November candidate planned
retro_2026 retrospective base_2026_nov Diagnostic planned
profile_2026 profile base_2026_nov Diagnostic planned
mcmc_2026 mcmc base_2026_nov Diagnostic planned
projection_2026 projection base_2026_nov OFL, maximum ABC, and scenarios planned
WarningUnresolved bridge source

The exact September 2025 post-CIE draft and model configuration still need to be identified. The 2024 September document is not an acceptable substitute.

Software Comparison Status Due Review role
RTMB exact_fixed_parameter validated not_applicable Supporting evidence for a future matched annual comparison
Rceattle close_fitted documented not_applicable Supporting evidence for a future matched annual comparison
SPoRC near_exact working 2026-08-25 Parallel model variant for the September 2026 review
NoteSPoRC September development

A near-exact SPoRC comparison has been completed in development, but its reproducible bridge script, exact paired ADMB configuration, checksums, and comparison tolerances still need to be recorded. The September review package is due August 25, 2026. Until that evidence is complete, SPoRC is a parallel model variant and not an operational replacement for Model 23.

Stage Decision needed Owner Status
author_preparation Confirm the CIE recommendations and the September 2025 responses that enter the 2026 bridge assessment_authors incomplete
september_review Approve bridge sequence and model set for the September draft assessment_authors_and_reviewers planned
september_review Determine the review role of the SPoRC parallel variant after the near-exact bridge package is complete assessment_authors_and_reviewers working
september_review Record which products are preliminary, carried forward, excluded, or final assessment_authors planned
november_review Replace preliminary inputs and record final delivery versions assessment_authors planned
author_final Select the author-recommended model and ABC assessment_authors not_started
plan_team_final Record Plan Team model and harvest recommendation BSAI_Groundfish_Plan_Team not_started
ssc_final Record SSC model and harvest recommendation NPFMC_SSC not_started
Bar chart counting 2026 assessment deliverables by status.
Deliverable Required check Status
Draft assessment for early September review Render, reconcile values, and label preliminary inputs working
Final November assessment Render, reconcile values, and verify replacements not_started
2024 reproduction and 2025 development bridge outputs Objective and key-output reconciliation planned
SPoRC parallel-model bridge package for the September review Near-exact bridge script, paired ADMB reference, input and output checksums, comparison tolerances, convergence evidence, updated OSA diagnostics, and rendered report working
Versioned annual model inputs File inventory, units, totals, and checksum review working
Base alternatives and diagnostic outputs Convergence and diagnostic checklist planned
Projection inputs outputs and scenario summaries Independent OFL and ABC check planned
CIE September Plan Team and SSC dispositions Match comments to actions and evidence incomplete

Edit the source records in assessment-years/2026/records/:

  • schedule.csv for dates and milestones;
  • the data delivery and validation table (data-sources.csv);
  • the model-run tracking table (model-runs.csv);
  • the parallel software comparison table (model-implementations.csv);
  • review-decisions.csv for decisions and dispositions; and
  • deliverables.csv for document and output readiness.

Commit and push the changes. GitHub Actions validates the records and renders the site automatically. To check the same changes locally before pushing, run:

Rscript scripts/validate_records.R
quarto render